THE THAMES BARRIER, LONDON

 

The Thames Barrier spans 520 metres across the River Thames near Woolwich, and it protects 125 square kilometres of central London from flooding caused by tidal surges. It has 10 steel gates that can be raised into position across the River Thames. When raised, the main gates stand as high as a 5-storey building and as wide as the opening of Tower Bridge. Each main gate weighs 3,300 tonnes.

The barrier is closed under storm surge conditions to protect London from flooding from the sea. It may also be closed during periods of high flow over Teddington Weir to reduce the risk of river flooding in some areas of west London including Richmond and Twickenham.

The Thames Barrier will then remain closed over high water until the water level downstream of the Thames Barrier has reduced to the same level as upstream. This is a managed process to provide for different circumstances and takes about 5 hours. The Thames Barrier is then opened, allowing the water upstream to flow out to sea with the outward-bound tide.

The Thames Estuary 2100 plan sets out how flood risk will be managed in the Thames estuary to the end of the century and beyond. It also recommends what actions the Environment Agency and others will need to take in the short term (the next 25 years), medium term (the following 15 years) and long term (to the end of the century). The plan is based on current guidance on climate change, but is adaptable to changes in predictions for sea level rise and climate change over the century.